Heathwall Sewage & Stormwater Pumping Station Building Nine Elms Lane SW8 5DA Data via plota.co.uk

Proposal

Proposed Refurbishment of Heathwall Sewage & Stormwater Pumping Station Building. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
9 Jul 2026
✓
Validated
21 Jul 2026
Decision
Target date was 6 Aug 2026

Under consideration

No decision has been issued yet. A decision is expected by 6 Aug 2026.

The consultation period closed on 11 Aug 2026.

Associated applications 4

  • Prior approvalPending2026/2511This application
    Proposed Refurbishment of Heathwall Sewage & Stormwater Pumping Station Building.
  • FullApprovedcouncil archive

    Conditions , , , , varied

Site constraints 8

Surface water flood riskHeliport CAA Height Restrictions
Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
National infrastructure project: Thames Tideway Tunnel
The site is inside the project boundary. Waste water treatment, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Archaeological priority area
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Wandsworth AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Surface water flood riskCouncil record
Recorded by the council for this site.
Council site ↗
Heliport CAA Height RestrictionsCouncil record
Recorded by the council for this site.
Council site ↗
Also on the record
Inside the Wandsworth built-up area; Public transport access: PTAL 6a (excellent), TfL 2023, for the 100 m square.
Not affected
Not green belt · No scheduled monument at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Wandsworth - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Wandsworth
Application type
Telecoms Application PD
Postcode
SW8 5DA
Received
9 Jul 2026
Validated
21 Jul 2026
Ward
St Mary's, St. Mary's Park - Historic, Nine Elms Ward, St. Mary's Ward
Case officer
Show
Target decision
6 Aug 2026
Applicant
Show
Agent
Steve Dunn

Consultation & key dates

Comments by
11 Aug 2026
Statutory expiry
11 Aug 2026
Wandsworth
Planning Authority Score
4.8/10
Below average
#164 of 296 councils
Relevant to this application:
Householder decisions

Wandsworth ranks #172 out of 296 councils for householder decision speed. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
Wandsworth decision statistics
Based on MHCLG data, the year to March 2026
90%
Overall approval rate
Above avg (87%) #120 of 296
92%
Householder approved
Above avg (90%) #168 of 296
62%
Decided in 8 weeks
Below avg (63%) #172 of 296
37%
Extended time limit
Below avg (41%) #124 of 296
89%
Minor dwellings approved
680 decided (1-9 homes)
81%
Major dwellings approved
16 decided (10+ homes)
72%
Change of use approved
36 decided
2,062
Total decisions
206 refused in the year to March 2026