Site Of Former Littlebrook Power Station Rennie Drive Dartford Kent DA1 5PT Data via plota.co.uk

26/01204/FUL - Full Application Awaiting decision

Proposal

Hybrid planning application for redevelopment of the site and surroundings, comprising: (i) Full planning application for the erection of a clean multi-energy charging and re-fuelling hub (including parking, welfare facilities and small scale retail), development platforms, hard/soft landscaping works, parking and access, energy and utilities infrastructure; and associated works; (ii) outline planning application for employment development (Use Classes B2 and/or B8) (all matters reserved excluding access). Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
19 Oct 2026
✓
Validated
22 Oct 2026
✓
Consultation
23 Oct 2026
Decision
Expected by 21 Jan 2027

Under consideration

No decision has been issued yet. Plota predicts a decision between 17 Dec 2026 and 12 Jan 2027, from Dartford's recent commercial and major works.

Comments are open until 17 Nov 2026

Comment on this application ↗

Documents 51

Statements & assessments 32

PDF PART 1 RISK ASSESSMENT AND REMEDIATION METHOD STATEMENT Report · 21 Oct 2026 View ↗ PDF PART 2 RISK ASSESSMENT AND REMEDIATION METHOD STATEMENT Report · 21 Oct 2026 View ↗ PDF PART 3 RISK ASSESSMENT AND REMEDIATION METHOD STATEMENT Report · 21 Oct 2026 View ↗ PDF PART 4 RISK ASSESSMENT AND REMEDIATION METHOD STATEMENT Report · 21 Oct 2026 View ↗ PDF PART 9 FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY Report · 21 Oct 2026 View ↗ PDF PART 8 FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY Report · 21 Oct 2026 View ↗ PDF PART 7 FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY Report · 21 Oct 2026 View ↗ PDF PART 6 FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY Report · 21 Oct 2026 View ↗ PDF PART 5 FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY Report · 21 Oct 2026 View ↗ PDF PART 4 FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY Report · 21 Oct 2026 View ↗ PDF PART 3 FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY Report · 21 Oct 2026 View ↗ PDF PART 2 FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY Report · 21 Oct 2026 View ↗ PDF PART 12 FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY Report · 21 Oct 2026 View ↗ PDF PART 11 FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY Report · 21 Oct 2026 View ↗ PDF PART 10 FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY Report · 21 Oct 2026 View ↗ PDF PART 1 FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY Report · 21 Oct 2026 View ↗ PDF DESIGN AND ACCESS STATEMENT Report · 16 Oct 2026 View ↗ PDF TRANSPORT ASSESSMENT APPS 1-5 Report · 16 Oct 2026 View ↗ PDF TRANSPORT ASSESSMENT APPS 6 -13 Report · 16 Oct 2026 View ↗ PDF TRANSPORT ASSESSMENT FINAL TEXT Report · 16 Oct 2026 View ↗ PDF AIR QUALITY ASSESSMENT Report · 16 Oct 2026 View ↗ PDF NOISE IMPACT ASSESSMENT Report · 16 Oct 2026 View ↗ PDF ECOLOGICAL ASSESSMENT Report · 16 Oct 2026 View ↗ PDF BNG REPORT PART 1 Report · 16 Oct 2026 View ↗ PDF BNG REPORT PART 2 Report · 16 Oct 2026 View ↗ PDF 14231. BIODIVERSITY_GAIN_PLAN FULL-AEGIS SIGNED Report · 16 Oct 2026 View ↗ PDF 14231. BIODIVERSITY_GAIN_PLAN OUTLINE-SIGNED AEGIS Report · 16 Oct 2026 View ↗ PDF ARBORICULTURAL IMPACT ASSESSMENT Report · 16 Oct 2026 View ↗ PDF SUSTAINABILITY AND ENERGY REPORT Report · 16 Oct 2026 View ↗ PDF EXTERNAL LIGHTING ASSESSMENT Report · 16 Oct 2026 View ↗ PDF STATEMENT OF COMMUNITY INVOLVEMENT Report · 16 Oct 2026 View ↗ PDF PLANNING STATEMENT COMBINED VF (UPDATED) Report · 16 Oct 2026 View ↗

All documents on the council site ↗

Site constraints 6

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Article 4 direction
HMO Article 4(1) Direction North Order 2025. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
National infrastructure project 652 m away: Riverside Energy Park
The site is 652 m from the project boundary. Generating station, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Habitat network: Network Enhancement Zone 2
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Also on the record
Radon affected area, class 2; Inside the Dartford built-up area.
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 24 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Dartford - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Dartford
Application type
Full Application
Postcode
DA1 5PT
Received
19 Oct 2026
Validated
22 Oct 2026
Ward
Bridge
Parish
Not Parished
Case officer
Show
Target decision
21 Jan 2027
Applicant
Show
Agent
Quod/Ms Helen Rodger

Decision outlook

Day 6 of the 56-day target. Dartford usually decides commercial and major works by day 63.

Day 657 days to the predicted decision (day 63)
50%decided within 8 weeks
100%approved
7%go to committee

Plota live figures for commercial and major works decided by Dartford in the last twelve months, from validation. Dartford decision record →

Public comments

No public comments yet.

32 neighbours consulted · Last counted 24 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15150711
Planning Portal ref
PP-15150711
Neighbours
23 Oct 2026
Consultation
23 Oct 2026
Comments by
17 Nov 2026
Statutory expiry
21 Jan 2027
Env. assessment
No
Dartford
Planning Authority Score
5/10
Average
#146 of 296 councils
Relevant to this application:
Householder decisions

Dartford is faster than most councils at deciding householder applications, ranking #92 out of 296. Dartford is also one of the strictest councils - it refuses more householder applications than almost any other, with only 80% approved vs 90% nationally.

One of the strictest councils
only 80% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
Dartford decision statistics
Based on MHCLG data, the year to March 2026
79%
Overall approval rate
Below avg (87%) #264 of 296
80%
Householder approved
Below avg (90%) #278 of 296
73%
Decided in 8 weeks
Above avg (63%) #92 of 296
33%
Extended time limit
Below avg (41%) #74 of 296
61%
Minor dwellings approved
46 decided (1-9 homes)
100%
Major dwellings approved
2 decided (10+ homes)
68%
Change of use approved
25 decided
595
Total decisions
126 refused in the year to March 2026