Ravenscourt Park Hospital,Ravenscourt Park,London,W6 0TU Data via plota.co.uk

P/2026/01981/DLBC - Details to Meet Conditions LBC REGISTERED: Pending recommendation

Proposal

Submission of Method Statement (Soft Strip, Historic Fabric & Schedule of Artefacts), in compliance with Condition 22 of Listed Building Consent dated 30 July 2026. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
31 Jul 2026
✓
Validated
3 Aug 2026
Decision
Target date was 28 Sept 2026

Under consideration

No decision has been issued yet. A decision is expected by 28 Sept 2026.

The consultation period closed on 25 Aug 2026.

Documents 154

Plans & drawings 147

PDF RCE - Strip Out and Protection Level B1 Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCE - Strip Out and Protection Level 02 Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCE - Strip Out and Protection Level 01 Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCE - Strip Out and Protection Level 0G Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCE - Strip Out West Elevation - Phase 1 - 2210-SPP-RCE-ZZ-DR-A-95-3004-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCE - Strip Out South Elevation - Phase 1 - 2210-SPP-RCE-ZZ-DR-A-95-3001-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCE - Strip Out Section 02 - Phase 1 - 2210-SPP-RCE-ZZ-DR-A-95-2002-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCE - Strip Out Section 01 - Phase 1 - 2210-SPP-RCE-ZZ-DR-A-95-2001-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCE - Strip Out North Elevation - Phase 1 - 2210-SPP-RCE-ZZ-DR-A-95-3003-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCE - Strip Out Level 01 RCP - Phase 1 - 2210-SPP-RCE-0G-DR-A-95-3503-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCE - Strip Out Level 01 Floor Finishes - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCE - Strip Out Level 0G RCP - Phase 1 - 2210-SPP-RCE-0G-DR-A-95-3502-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCE - Strip Out Level 0G Floor Finishes - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCE - Strip Out East Elevation - Phase 1 - 2210-SPP-RCE-ZZ-DR-A-95-3002-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCE - Strip Out and Protection Roof Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out Level B1 Floor Finishes - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out Level 03 RCP - Phase 1 - 2210-SPP-RCD-03-DR-A-95-3505-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out Level 03 Floor Finishes - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out Level 02 RCP - Phase 1 - 2210-SPP-RCD-02-DR-A-95-3504-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out Level 02 Floor Finishes - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out Level 01 RCP - Phase 1 - 2210-SPP-RCD-01-DR-A-95-3503-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out Level 01 Floor Finishes - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out Level 0G RCP - Phase 1 - 2210-SPP-RCD-0G-DR-A-95-3502-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out Level 0G Floor Finishes - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out East Elevation - Phase 1 - 2210-SPP-RCD-ZZ-DR-A-95-3002-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out and Protection Roof Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out and Protection Level B1 Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out and Protection Level 03 Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out and Protection Level 02 Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out and Protection Level 01 Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out and Protection Level 0G Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out West Elevation - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out South Elevation - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out Section 02 - Phase 1 - 2210-SPP-RCD-ZZ-DR-A-95-2002-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out Section 01 - Phase 1 - 2210-SPP-RCD-ZZ-DR-A-95-2001-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out North Elevation - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCD - Strip Out Level B1 RCP - Phase 1 - 2210-SPP-RCD-B1-DR-A-95-3501-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out and Protection Level 02 Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out and Protection Level 01 Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out and Protection Level 0G Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out West Elevation - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out South Elevation - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out Section 02 - Phase 1 - 2210-SPP-RCC-ZZ-DR-A-95-2002-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out Section 01 - Phase 1 - 2210-SPP-RCC-ZZ-DR-A-95-2001-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out North Elevation - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out Level B1 RCP - Phase 1 - 2210-SPP-RCC-B1-DR-A-95-3501-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out Level 04 RCP - Phase 1 - 2210-SPP-RCC-04-DR-A-95-3506-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out Level 04 Floor Finishes - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out Level 03 RCP - Phase 1 - 2210-SPP-RCC-03-DR-A-95-3505-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out Level 03 Floor Finishes - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out Level 02 RCP - Phase 1 - 2210-SPP-RCC-02-DR-A-95-3504-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out Level 02 Floor Finishes - Phase 1 - 2210-SPP-RCC-02-DR-A-95-4004-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out Level 01 RCP - Phase 1 - 2210-SPP-RCC-01-DR-A-95-3503-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out Level 01 Floor Finishes - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out Level 0G RCP - Phase 1 - 2210-SPP-RCC-0G-DR-A-95-3502-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out Level 0G Floor Finishes - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out East Elevation - Phase 1 - 2210-SPP-RCC-ZZ-DR-A-95-3002-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out and Protection Roof Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out and Protection Level B1 Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out and Protection Level 04 Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCC - Strip Out and Protection Level 03 Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Childrens Wards - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 05 RCP - Part 1 - Phase 1 - 2210-SPP-RCB-05-DR-A-95-3513-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 04 RCP - Part 2 - Phase 1 - 2210-SPP-RCB-04-DR-A-95-3512-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 04 RCP - Part 1 - Phase 1 - 2210-SPP-RCB-04-DR-A-95-3511-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 03 RCP - Part 2 - Phase 1 - 2210-SPP-RCB-03-DR-A-95-3510-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 03 RCP - Part 1 - Phase 1 - 2210-SPP-RCB-03-DR-A-95-3509-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 02 RCP - Part 2 - Phase 1 - 2210-SPP-RCB-02-DR-A-95-3508-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 02 RCP - Part 1 - Phase 1 - 2210-SPP-RCB-02-DR-A-95-3507-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 01 RCP - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 01 RCP - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 0G RCP - Part 2 - Phase 1 - 2210-SPP-RCB-0G-DR-A-95-3504-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 0G RCP - Part 1 - Phase 1 - 2210-SPP-RCB-0G-DR-A-95-3503-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out East Elevation - Phase 1 - 2210-SPP-RCB-ZZ-DR-A-95-3001-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Waiting Room Level 03 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Waiting Room Level 02 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Waiting Room Level 01 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Waiting Room Level 0G - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Roof Plan - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Roof Plan - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection NW and NE Stairs - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Level B1 Floor Plan - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Level B1 Floor Plan - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Level 05 Floor Plan - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Level 05 Floor Plan - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Level 04 Floor Plan - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Level 04 Floor Plan - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Level 03 Floor Plan - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Level 03 Floor Plan - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Level 02 Floor Plan - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Level 02 Floor Plan - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Level 01 Floor Plan - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Level 01 Floor Plan - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Level 0G Floor Plan - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out and Protection Level 0G Floor Plan - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out West Elevation - Phase 1 - 2210-SPP-RCB-ZZ-DR-A-95-3003-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out South Elevation - Phase 1 - 2210-SPP-RCB-ZZ-DR-A-95-3002-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Section 03 - Phase 1 - 2210-SPP-RCB-ZZ-DR-A-95-2003-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Section 02 - Phase 1 - 2210-SPP-RCB-ZZ-DR-A-95-2002-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Section 01 - Phase 1 - 2210-SPP-RCB-ZZ-DR-A-95-2001-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out North Elevation - Phase 1 - 2210-SPP-RCB-ZZ-DR-A-95-3004-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level B1 RCP - Part 2 - Phase 1 - 2210-SPP-RCB-B1-DR-A-95-3502-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level B1 RCP - Part 1 - Phase 1 - 2210-SPP-RCB-B1-DR-A-95-3501-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 05 RCP - Part 2 - Phase 1 - 2210-SPP-RCB-05-DR-A-95-3514-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 05 Floor Finishes - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 05 Floor Finishes - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 04 Floor Finishes - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 04 Floor Finishes - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 03 Floor Finishes - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 03 Floor Finishes - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 02 Floor Finishes - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 02 Floor Finishes - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 01 Floor Finishes - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 01 Floor Finishes - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 0G Floor Finishes - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level 0G Floor Finishes - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level B1 Floor Finishes - Part 2 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCB - Strip Out Level B1 Floor Finishes - Part 1 - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out and Protection Grand Entrance - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out and Protection Roof Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out and Protection Level 03 Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out and Protection Level 02 Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out and Protection Level 1M Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out and Protection Level 01 Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out and Protection Level 0G Floor Plan - Phase 1.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out Level 02 RCP - Phase 1 - 2210-SPP-RCA-02-DR-A-95-3504-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out Level 02 Floor Finishes - Phase 1 - 2210-SPP-RCA-02-DR-A-95-4004-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out Level 1M RCP - Phase 1 - 2210-SPP-RCA-1M-DR-A-95-3503-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out Level 1M Floor Finishes - Phase 1 - 2210-SPP-RCA-1M-DR-A-95-4003-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out Level 01 RCP - Phase 1 - 2210-SPP-RCA-01-DR-A-95-3502-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out Level 01 Floor Finishes - Phase 1 - 2210-SPP-RCA-01-DR-A-95-4002-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out East Elevation - Phase 1 - 2210-SPP-RCA-ZZ-DR-A-95-3001-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out West Elevation - Phase 1 - 2210-SPP-RCA-ZZ-DR-A-95-3003-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out South Elevation - Phase 1 - 2210-SPP-RCA-ZZ-DR-A-95-3002-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out Section 02 - Phase 1 - 2210-SPP-RCA-ZZ-DR-A-95-2002-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out Section 01 - Phase 1 - 2210-SPP-RCA-ZZ-DR-A-95-2001-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out North Elevation - Phase 1 - 2210-SPP-RCA-ZZ-DR-A-95-3004-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out Level 03 RCP - Phase 1 - 2210-SPP-RCA-03-DR-A-95-3505-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF RCA - Strip Out Level 03 Floor Finishes - Phase 1 - 2210-SPP-RCA-03-DR-A-95-4005-S4-P01.pdf Drawing · 3 Aug 2026 View ↗ PDF 2210-SPP-RC-XX-ID-A-XX-6002 SPP Strip Out - Phase 1 - Drawings Issue Sheet.pdf Other Reports · 3 Aug 2026 View ↗ PDF Masterplan - Demolition Access Plan - Level B1 - 2210-SPP-RCZ-0G-DR-A-95-1091-S4-P01.pdf Report · 3 Aug 2026 View ↗ PDF Masterplan - Demolition Access Plan - Level 05 - 2210-SPP-RCZ-0G-DR-A-95-1097-S4-P01.pdf Report · 3 Aug 2026 View ↗ PDF Masterplan - Demolition Access Plan - Level 04 - 2210-SPP-RCZ-0G-DR-A-95-1096-S4-P01.pdf Report · 3 Aug 2026 View ↗ PDF Masterplan - Demolition Access Plan - Level 03 - 2210-SPP-RCZ-0G-DR-A-95-1095-S4-P01.pdf Report · 3 Aug 2026 View ↗ PDF Masterplan - Demolition Access Plan - Level 02 - 2210-SPP-RCZ-0G-DR-A-95-1094-S4-P01.pdf Report · 3 Aug 2026 View ↗ PDF Masterplan - Demolition Access Plan - Level 01 - 2210-SPP-RCZ-0G-DR-A-95-1093-S4-P01.pdf Report · 3 Aug 2026 View ↗ PDF Masterplan - Demolition Access Plan - Level 0G - 2210-SPP-RCZ-0G-DR-A-95-1092-S4-P01.pdf Report · 3 Aug 2026 View ↗

All documents on the council site ↗

Associated applications 3

Site constraints 9

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Ravenscourt & Starch Green conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
National infrastructure project: Thames Tideway Tunnel
The site is inside the project boundary. Waste water treatment, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Air quality management area: Hammersmith and Fulham AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
12 listed buildings within 150 m
Nearest: Royal Masonic Hospital, With Associated Boundary Walls, Gates, Railings and Planters, Grade II*, 59 m away · 1 Grade II*, 11 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 12 with distances
Historic England ↗
Also on the record
Heritage at risk 58 m away: Former Royal Masonic Hospital, Ravenscourt Park, Hammersmith; Inside the Hammersmith and Fulham built-up area; Public transport access: PTAL 4 (good), TfL 2023, for the 100 m square; Designated open space 39 m away.
Not affected
Not green belt · No scheduled monument at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Hammersmith and Fulham - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Details to Meet Conditions LBC
Postcode
W6 0TU
Received
31 Jul 2026
Validated
3 Aug 2026
Ward
Ravenscourt
Case officer
Show
Agent
Jiyoon Jeong / Turley

Consultation & key dates

Consultation
4 Aug 2026
Comments by
25 Aug 2026
Statutory expiry
28 Sept 2026
Hammersmith and Fulham
Planning Authority Score
3.7/10
Below average
#210 of 296 councils
Relevant to this application:
Householder decisions

Hammersmith and Fulham is one of the slowest councils in England for householder decisions, ranking #281 out of 296. The council extends the time limit on 63% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are more likely to be approved here than most councils, with a 99% approval rate vs 90% nationally.

Among the slowest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Hammersmith and Fulham decision statistics
Based on MHCLG data, the year to March 2026
95%
Overall approval rate
Above avg (87%) #20 of 296
99%
Householder approved
Above avg (90%) #4 of 296
33%
Decided in 8 weeks
Below avg (63%) #281 of 296
63%
Extended time limit
Above avg (41%) #275 of 296
97%
Minor dwellings approved
209 decided (1-9 homes)
100%
Major dwellings approved
1 decided (10+ homes)
92%
Change of use approved
37 decided
1,321
Total decisions