From Proposed South Yell Substation To Energy Isles Connection At North Yell, Shetland Data via plota.co.uk

2026/121/ECUCON - Energy Consents Unit Decided

Proposal

Pre-Application Consultation Notice, SSEN Transmission - PAC 2 Alignment Options- Energy Isles 132kV OHL, Yell. Shetland Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
3 Jun 2026
✓
Pre-app Complete
25 Jun 2026

Pre-app Complete on 25 Jun 2026 · Delegated Decision · Last checked 2 Sept 2026

Site constraints 1

Also on the record
Radon affected area, class 2.
Not affected
Outside flood zones 2 and 3 · No scheduled monument at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Shetlands - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Shetlands
Application type
Energy Consents Unit
Postcode
ZE2 9DD
Received
3 Jun 2026
Validated
3 Jun 2026
Case officer
Show
Target decision
1 Jul 2026
Decision
Pre-app Complete
Decision date
25 Jun 2026
Decision level
Delegated Decision
Applicant
Show

Public comments

No public comments yet.

Last counted 2 Sept 2026

Read the comments on the council site ↗

Consultation & key dates

Statutory expiry
1 Jul 2026
Env. assessment
No