Variation of Condition 2 (Approved Plans) of approved application granted 22/09/2023 for: Variation of Condition 2 (Approved Plans) & Condition 3 (Surface Water Drainage) of approved application granted 25.10.2022 for: A new kilovolt (kV) Grid Supply Point (GSP) substation including two supergrid transformers, associated buildings, equipment and switchgear, a single circuit cable sealing end compound, a new permanent vehicular access to the public highway, associated landscaping (including boundary fencing, an area for Biodiversity Net Gain, and landscape mounding) and drainage. Variation would allow for: Change in layout of substation. Data via plota.co.uk
Last checked
Associated applications 5
Site constraints 5
Checked on 17 October 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.
Every application in Braintree - and every UK council - as a live feed, an API, or a bulk CSV export.
Nearby new applications
Bramford To Twinstead National Grid Project
Formal Submission - Stage 4, 5 and 6 Geoarchaeology DWSI In Accordance with Requ...
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Requirement�8(1) Retention and Removal of Tree...
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Schedule 3; Requirement 8 Retention and Remova...
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Requirement 8(1) Retention and Removal of Tree...
Bramford To Twinstead National Grid Project
Formal Submission - Stage 5 Retention and Removal of Trees, Woodlands and Hedger...
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Detials reserved by Requirement 14 - Soil Management Plan for Stag...
Braintree is faster than most councils at deciding householder applications, ranking #47 out of 296. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).
Referenced application
Council archive
Land Adjacent Butlers Wood And Waldergrave Wood West Of A131 Sudbury Road Twinstead Essex
Variation of Condition 2 (Approved Plans) & Condition 3 (Surface Water Drainage) of approved application 22/01147/FUL granted 25.10.2022 for: A new 400/132 kilovolt (kV) Grid Supply Point (GSP) substation including two supergrid transformers, associated buildings, equipment and switchgear, a single circuit cable sealing end compound, a new permanent vehicular access to the public highway, associated landscaping (including boundary fencing, an area for Biodiversity Net Gain, and landscape mounding) and…
- Received
- 6 Jun 2023
- Outcome
- Pending
- Type
- Amendment
Land Adjacent Butlers Wood And Waldergrave Wood West Of A131 (In The Parishes Of Bulmer And Twinstead) Sudbury Road Bulmer Essex
A new 400/132 kilovolt (kV) Grid Supply Point (GSP) substation including two supergrid transformers, associated buildings, equipment and switchgear, a single circuit cable sealing end compound, a new permanent vehicular access to the public highway, associated landscaping (including boundary fencing, an area for Biodiversity Net Gain, and landscape mounding) and drainage
- Received
- 29 Apr 2022
- Decided
- 25 Oct 2022
- Outcome
- Approved