Plot 1.02 & 1.03, Land at Greenwich Peninsula, South of the O2, SE10 Data via plota.co.uk

26/1043/NM - Non Material Approved

Proposal

An application submitted under Section 96a of the Town & Country Planning Act 1990 for a non-material amendment in connection with Reserved Matters Approval dated 23/11/2023 (Reference: ) for Submission of Reserved Matters Application (Access, Appearance, Landscaping, Layout and Scale) pursuant to Condition 13 of Outline Planning Permission dated 8th December 2015 for Plots 1.02 and 1.03 comprising 866 build to rent residential units (Use Class C3), ancillary spaces and cycle store, 239sqm retail unit (Use Class A1-A5), and associated landscaping, parking, access and associated works. This amendment seeks: Alterations to the approved design by varying the approved drawings listed under condition 1; and Modifications to the wording of the description of development Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
31 Mar 2026
✓
Approved
13 May 2026

Approved on 13 May 2026 · Delegation · Last checked 6 Jul 2026

Documents 145

Plans & drawings 118

PDF 0857-jca-zz-01-dr-a-06101_p05 Proposed level 01 plan Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-14-dr-a-06103_p05 Proposed level 14 plan Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-19-dr-a-06106_p05 Proposed level 19 plan Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-20-dr-a-06107_p05 Proposed level 20 plan Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-g0-dr-a-06100_p05 Proposed ground floor plan Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-rf-dr-a-06108_p05 Proposed roof plan Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-zz-dr-a-06102_p05 Proposed level 02-13 plan Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-zz-dr-a-06104_p05 Proposed level 15-16 plan Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-zz-dr-a-06105_p05 Proposed level 17-18 plan Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-01-dr-a-06131_p03 Cycle hub - proposed level 01 plan Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-02-dr-a-06132_p03 Cycle hub - proposed level 02 plan Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-g0-dr-a-06130_p03 Cycle hub - proposed ground floor plan Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-rf-dr-a-06133_p03 Cycle hub - proposed roof plan Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-xx-dr-a-06200_p05 Elevation - east facade Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-xx-dr-a-06201_p05 Elevation - north facade Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-xx-dr-a-06203_p05 Elevation - west facade Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-xx-dr-a-06210_p03 Proposed cycle hub south and west elevations Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-xx-dr-a-06211_p03 Proposed cycle hub north and east elevations Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-xx-dr-a-06240_p04 Bay type elevation - east facade Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-xx-dr-a-06241_p04 Bay type elevation - west facade Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-xx-dr-a-06242_p05 Bay type elevation - west facade Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-xx-dr-a-06243_p04 Bay type elevation - south east facade Revised Drawing · 5 May 2026 View ↗ PDF 0857-jca-zz-xx-dr-a-06310_p03 Proposed cycle hub section a-a and section b-b Revised Drawing · 5 May 2026 View ↗ PDF Commercial units layout strategy Document · 5 May 2026 View ↗ PDF Plot 1.03 - eb.2 - j unit layout 1bed 2person adaptable Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - eb.2 - k unit layout studio Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - eb.2 - l unit layout 2bed 4person Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - eb.1 -1bed 2person Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - eb.2 - d unit layout 1bed 2person Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - eb.2 - e unit layout studio Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - eb.2 - f unit layout studio Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - eb.2 - g unit layout 1bed 2person Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - eb.2 - h unit layout studio Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - eb.2 - i unbed 3person Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - wb.2 - i unit layout 1bed 2person Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - wb.2 - j unit layout studio Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - wb.2 - a unit layout 2bed 4person Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - eb.2 - a unit layout 2bed 4person Drawing · 31 Mar 2026 View ↗ PDF Ot 1.03 - eb.2 - bbed 2person Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - eb.2 - c unit layout 3bed 5person Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - wb.2 - c unit layout studio Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - wb.2 - d unit layout 2bed 4person Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - wb.2 - e unit layout 2bed 4person Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - wb.2 - f unit layout 1bed 2person adaptable Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - unit type wb.2 - g 2 bed 4 person adaptable m4(3) Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - wb.2 - h unit layout 2bed 4person Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - west tower - north facade detail Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - east tower - south facade detail base Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - east tower - east facade detail typical Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - east tower - east facade detail top Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - podium - north facade detail Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - wb.2 - b unit layout 1bed 2person Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - east west section through lobby looking north Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - west tower north south section through core Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - east tower north south section through core Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - east west section through arcade and commercial area Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - masterplan - north south section through lobby in existing & rma mas Drawing · 31 Mar 2026 View ↗ PDF Proposed cycle hub section a-a and section b-b Drawing · 31 Mar 2026 View ↗ PDF Bay type elevation - west facade Drawing · 31 Mar 2026 View ↗ PDF Proposed section aa Drawing · 31 Mar 2026 View ↗ PDF Proposed section bb Drawing · 31 Mar 2026 View ↗ PDF Proposed section cc Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - masterplan - east west section through lobby in existing & rma maste Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - north south section through lobby looking west Drawing · 31 Mar 2026 View ↗ PDF Masterplan - north elevation in existing & rma masterplan context Drawing · 31 Mar 2026 View ↗ PDF Proposed cycle hub south and west elevations Drawing · 31 Mar 2026 View ↗ PDF Proposed cycle hub north and east elevations Drawing · 31 Mar 2026 View ↗ PDF Bay type elevation - south east facade Drawing · 31 Mar 2026 View ↗ PDF Bay type elevation - east facade Drawing · 31 Mar 2026 View ↗ PDF Bay type elevation - west facade Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - south elevation in existing & rma masterplan context Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - west elevation in existing & rma masterplan context Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - north elevation in existing & rma masterplan context Drawing · 31 Mar 2026 View ↗ PDF Plot 1.03 - east elevation in existing & rma masterplan context Drawing · 31 Mar 2026 View ↗ PDF Masterplan - south elevation in existing & rma masterplan context Drawing · 31 Mar 2026 View ↗ PDF Masterplan - west elevation in existing & rma masterplan context Drawing · 31 Mar 2026 View ↗ PDF Apartment layouts - unit type 11 Drawing · 31 Mar 2026 View ↗ PDF Elevation - west facade Drawing · 31 Mar 2026 View ↗ PDF Elevation - east facade Drawing · 31 Mar 2026 View ↗ PDF Elevation - north facade Drawing · 31 Mar 2026 View ↗ PDF Elevation - south facade Drawing · 31 Mar 2026 View ↗ PDF Masterplan - east elevation in existing & rma masterplan context Drawing · 31 Mar 2026 View ↗ PDF Apartment layouts - unit type 6 Drawing · 31 Mar 2026 View ↗ PDF Apartment layouts - unit type 7 Drawing · 31 Mar 2026 View ↗ PDF Apartment layouts - unit type 8a Drawing · 31 Mar 2026 View ↗ PDF Apartment layouts - unit type 8b Drawing · 31 Mar 2026 View ↗ PDF Apartment layouts - unit type 9 Drawing · 31 Mar 2026 View ↗ PDF Apartment layouts - unit type 10 Drawing · 31 Mar 2026 View ↗ PDF Proposed ground floor plan Drawing · 31 Mar 2026 View ↗ PDF Apartment layouts - unit type 1 Drawing · 31 Mar 2026 View ↗ PDF Apartment layouts - unit type 2 Drawing · 31 Mar 2026 View ↗ PDF Apartment layouts - unit type 3 Drawing · 31 Mar 2026 View ↗ PDF Apartment layouts - unit type 4 Drawing · 31 Mar 2026 View ↗ PDF Apartment layouts - unit type 5 Drawing · 31 Mar 2026 View ↗ PDF Proposed plot 1.03 level 00 floor Drawing · 31 Mar 2026 View ↗ PDF Proposed plot 1.03 level 00 - mezzanine floor Drawing · 31 Mar 2026 View ↗ PDF Proposed plot 1.03 roof level Drawing · 31 Mar 2026 View ↗ PDF Proposed roof plan Drawing · 31 Mar 2026 View ↗ PDF Proposed level 01 plan Drawing · 31 Mar 2026 View ↗ PDF Proposed level 02 plan Drawing · 31 Mar 2026 View ↗ PDF Proposed plot 1.03 level 22-27 floor Drawing · 31 Mar 2026 View ↗ PDF Proposed plot 1.03 level 28 floor Drawing · 31 Mar 2026 View ↗ PDF Proposed plot 1.03 level 29-30 floor Drawing · 31 Mar 2026 View ↗ PDF Proposed plot 1.03 level 31-33 floor Drawing · 31 Mar 2026 View ↗ PDF Proposed plot 1.03 level 34 floor Drawing · 31 Mar 2026 View ↗ PDF Proposed plot 1.03 basement floor Drawing · 31 Mar 2026 View ↗ PDF Proposed level 02-13 plan Drawing · 31 Mar 2026 View ↗ PDF Proposed level 15-16 plan Drawing · 31 Mar 2026 View ↗ PDF Proposed level 17-18 plan Drawing · 31 Mar 2026 View ↗ PDF Proposed plot 1.03 level 01 floor Drawing · 31 Mar 2026 View ↗ PDF Proposed plot 1.03 level 02-20 floor Drawing · 31 Mar 2026 View ↗ PDF Proposed plot 1.03 level 21 floor Drawing · 31 Mar 2026 View ↗ PDF Proposed level 01 plan Drawing · 31 Mar 2026 View ↗ PDF Proposed level 14 plan Drawing · 31 Mar 2026 View ↗ PDF Proposed level 19 plan Drawing · 31 Mar 2026 View ↗ PDF Proposed level 20 plan Drawing · 31 Mar 2026 View ↗ PDF Proposed ground floor plan Drawing · 31 Mar 2026 View ↗ PDF Proposed roof plan Drawing · 31 Mar 2026 View ↗

All documents on the council site ↗

Associated applications 4

Site constraints 9

Flood zone 2, rivers and sea
Medium chance: between a 1 in 100 and 1 in 1,000 annual chance from rivers, or 1 in 200 to 1 in 1,000 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Archaeological priority area
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Greenwich AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project about 305 m away: Silvertown Tunnel
The site is about 305 m from the project boundary. Highway, decided. The project page says whether consent was granted. Also within 2 km: Thames Tideway Tunnel (decided, about 480 m); London Strategic Heat Main Project (at pre-application, about 1048 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Habitat network: Network Enhancement Zone 2
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
1 listed building within 150 m of the postcode pin; Inside the Greenwich built-up area; Public transport access: PTAL 5 (very good), TfL 2023, for the 100 m square.
Not affected
Not green belt · No scheduled monument at the site

Checked on 6 October 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Greenwich - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Greenwich
Application type
Non Material
Postcode
SE10 0DY
Received
31 Mar 2026
Validated
31 Mar 2026
Ward
GREENWICH PENINSULA
Parish
Greenwich
Case officer
Show
Target decision
14 May 2026
Decision
Approve
Decision date
13 May 2026
Decision level
Delegation
Agent
Quod

Consultation & key dates

Alt. reference
PP-14807253
Planning Portal ref
PP-14807253
Statutory expiry
28 Apr 2026
Env. assessment
No
Greenwich
Planning Authority Score
5.4/10
Average
#123 of 296 councils
Relevant to this application:
Householder decisions

Greenwich is faster than most councils at deciding householder applications, ranking #76 out of 296. Only 29% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Greenwich is also one of the strictest councils - it refuses more householder applications than almost any other, with only 78% approved vs 90% nationally.

One of the strictest councils
only 78% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
Greenwich decision statistics
Based on MHCLG data, the year to March 2026
77%
Overall approval rate
Below avg (87%) #278 of 296
78%
Householder approved
Below avg (90%) #287 of 296
75%
Decided in 8 weeks
Above avg (63%) #76 of 296
29%
Extended time limit
Below avg (41%) #49 of 296
60%
Minor dwellings approved
114 decided (1-9 homes)
100%
Major dwellings approved
13 decided (10+ homes)
66%
Change of use approved
195 decided
1,468
Total decisions
331 refused in the year to March 2026