Central Electricity Generating Board Calow Lane Calow Chesterfield S44 5XH Data via plota.co.uk
Proposal
Section 37 Consent for overhead line works to tie in existing network to new 400kV Substation (to include provision of temporary lines, temporary and permanent tower installation, and removal of overhead lines and pylons) Data via plota.co.uk
Application progress
Approved on 13 Aug 2026 · Last checked 15 Aug 2026
Work with planning data? Every application in North East Derbyshire - and every UK council - as a live feed or API. About Plota's data service
Important details
- Council
- North East Derbyshire
- Postcode
- S44 5XH
- Received
- 19 Jun 2026
- Validated
- 19 Jun 2026
- Target decision
- 14 Aug 2026
- Decision
- NO OBJECTION
- Decision date
- 13 Aug 2026
Public comments
1 neighbour consulted · Last counted 15 Aug 2026
Consultation & key dates
- Neighbours
- 26 Jun 2026
- Consultation
- 26 Jun 2026
- Comments by
- 17 Jul 2026
Historical activity at this location
4 previous applications on record - archival context, not part of the live application.
Previous applications at this address
North East Derbyshire ranks #166 out of 296 councils for householder decision speed. Householder applications are slightly more likely to be approved here (93%) than the national average (90%).
Track this application
Central Electricity Generating Board Calow Lane Calow Chesterfield S44 5XH
Tracking this application
Not there in a minute? Check junk - especially Hotmail and Outlook.
Go to your dashboard →