Waltham Cross to Tottenham Substation, near to Highbridge Street, Waltham Abbey Data via plota.co.uk
Description
Application to discharge Requirement 13 (Stage 5a) - Construction Environment Management Plan by National Grid Electricity Transmission plc for an Order Granting Development Consent for the North London Reinforcement Project for the uprating of an existing 275kV transmission line of approximately 14km in length from Waltham Cross substation to Tottenham substation to enable it to run at a voltage of 400kV, together with associated development. Data via plota.co.uk
Nearby new applications
7, King George Road, Waltham Abbey, EN9 1HG
Prior notification application for proposed 6m deep single storey rear extension
Land to the side and rear of , 41 Townmead Road, Waltham Abbey, EN9 1RP
Approval of Details Reserved by Condition 3B Contaminated land Verification of E...
Highbridge Retail Park, Highbridge Street, Waltham Abbey, EN9 1BY
Amalgamation of Units 2 and 3.
34, Foresters Den Abbey Nursery, Sun Street, Waltham Abbey, EN9 1EJ
Expansion of existing nursery into a disused outbuildings in the rear of 34 Sun ...
34, Foresters Den Abbey Nursery, Sun Street, Waltham Abbey, EN9 1EJ
Listed Building Consent for expansion of existing nursery into disused outbuildi...
Waltham Cross to Tottenham Substation, near to Highbridge Street, Waltham Abbey
Application to discharge Requirement 13 (Stage 5b) - Construction Environment Ma...
Epping Forest ranks #111 out of 292 councils for householder decision speed. Epping Forest is also one of the strictest councils - it refuses more householder applications than almost any other, with only 74% approved vs 90% nationally.